| T & C
Job No: |
|
411 |
| Project Name: |
|
Sienna Flat Bank Creek Pump Station |
| Owner: |
|
Sienna Plantation LID |
| Engineer: |
|
LJA Engineering |
| Project Size: |
|
$1,710,000.00 |
| Completion Date: |
|
March-07 |
|
|
|
| T & C Job
No: |
|
433 |
| Project Name: |
|
Downtown Drainage Improvements |
| Owner: |
|
City of Corpus Christi |
| Engineer: |
|
Urban Engineering |
| Project Size: |
|
$5,608,420.00 |
| Completion Date: |
|
May-07 |
|
|
|
| T & C Job
No: |
|
451 |
| Project Name: |
|
Water Plant Pump Station #1 |
| Owner: |
|
West Harris County Regional Water Auth. |
| Engineer: |
|
Dannenbaum Engineering |
| Project Size: |
|
$16,500,000.00 |
| Completion Date: |
|
Oct-08 |
|
|
|
| T & C Job
No: |
|
455 |
| Project Name: |
|
Haymarket Lift Station |
| Owner: |
|
Harris County F.W.S.D. #51 |
| Engineer: |
|
Pate Engineers |
| Project Size: |
|
$1,031,000.00 |
| Completion Date: |
|
September-07 |
|
|
|
| T & C Job
No: |
|
456 |
| Project Name: |
|
NW 20 WWTP Expansion |
| Owner: |
|
Northwest Harris County MUD #20 |
| Engineer: |
|
R G Miller Engineers |
| Project Size: |
|
$1,808,000.00 |
| Completion Date: |
|
Jan-08 |
|
|
|
| T & C Job
No: |
|
466 |
| Project Name: |
|
WWTP LS & Phase IV WWTP |
| Owner: |
|
Fort Bend MUD #34 |
| Engineer: |
|
Carter & Burgess, Inc. |
| Project Size: |
|
$1,328,000.00 |
| Completion Date: |
|
Mar-08 |
|
|
|
| T & C Job
No: |
|
472 |
| Project Name: |
|
0.24 GPD WWTP (Phase I) |
| Owner: |
|
Chambers County ID #1 |
| Engineer: |
|
Bury+Partners |
| Project Size: |
|
$1,974,168.00 |
| Completion Date: |
|
May-09 |
|
|
|
| T & C Job
No: |
|
474 |
| Project Name: |
|
WWTP No. 1 |
| Owner: |
|
Fort Bend County MUD #134 |
| Engineer: |
|
LJA Engineering |
| Project Size: |
|
$1,010,599 |
| Completion Date: |
|
Aug-08 |
|
|
|
| T & C Job
No: |
|
477 |
| Project Name: |
|
WWTP No. 1 (Phase 1) |
| Owner: |
|
Willow Creek Farms MUD |
| Engineer: |
|
Pate Engineers |
| Project Size: |
|
$756,500 |
| Completion Date: |
|
Jul-09 |
|
|
|
| T & C Job
No: |
|
482 |
| Project Name: |
|
Pump and Control Building, Paving,
Drainage, Yard Piping at WP #5 |
| Owner: |
|
SJRA |
| Engineer: |
|
Brown & Gay Engineers, Inc. |
| Project Size: |
|
$3,915,833.00 |
| Completion Date: |
|
May-10 |
|
|
|
| T & C Job
No: |
|
484 |
| Project Name: |
|
54" Water Line from Greens Road to West
Rankin Road |
| Owner: |
|
NHCRWA |
| Engineer: |
|
Pate Engineers, Inc. |
| Project Size: |
|
$1,097,055.00 |
| Completion Date: |
|
Jul-09 |
|
|
|
| T & C Job
No: |
|
486 |
| Project Name: |
|
LS Improvements |
| Owner: |
|
Bacliff MUD |
| Engineer: |
|
Freese & Nichols |
| Project Size: |
|
$841,979 |
| Completion Date: |
|
Jun-09 |
|
|
|
| T & C Job
No: |
|
488 |
| Project Name: |
|
Lift Station Phase 2 |
| Owner: |
|
Fort Bend MUD #121 |
| Engineer: |
|
LJA Engineering |
| Project Size: |
|
$378,097.00 |
| Completion Date: |
|
Jan-09 |
|
|
|
| T & C Job
No: |
|
493 |
| Project Name: |
|
0.835 MGD WWTP Rehabilitation |
| Owner: |
|
Harris County MUD #8 |
| Engineer: |
|
Century Engineering, Inc. |
| Project Size: |
|
$1,465,000.00 |
| Completion Date: |
|
Nov-09 |
|
|
|
| T & C Job
No: |
|
494 |
| Project Name: |
|
0.35 MGD WWTP Conversion |
| Owner: |
|
Greens Parkway MUD |
| Engineer: |
|
Huitt-Zollars, Inc. |
| Project Size: |
|
$1,657,004.00 |
| Completion Date: |
|
Dec-09 |
|
|
|
| T & C Job
No: |
|
499 |
| Project Name: |
|
Stewart Creek WWTP |
| Owner: |
|
City of Montgomery |
| Engineer: |
|
Bleyl & Associates |
| Project Size: |
|
$1,767,000 |
| Completion Date: |
|
Dec-09 |
|


 |
|
|
|