T & C  Job  No: 325    
Project Name: Storm water Pump Stations @ IAH
Owner:   City of Houston    
Engineer:   P,B, S, & J  /  Stiver  
Project Size: $4,450,000    
Completion Date: Dec-03    
       
T & C  Job  No: 381    
Project Name: Resaca Lift Station
Owner:   City of Corpus Christi (Holoman)
Engineer:   Maverick Engineering  
Project Size $1,040,000.00  
Completion Date June-05    
       
T & C  Job  No: 411    
Project Name: Sienna Flat Bank Creek Pump Station
Owner:   Sienna Plantation LID  
Engineer:   LJA Engineering  
Project Size: $1,710,000.00  
Completion Date: March-07    
       
T & C  Job  No: 430    
Project Name: 0.240 MGD Wastewater Treatment Plant
Owner:   Fort Bend MUD #152  
Engineer:   Pate Engineers    
Project Size: $559,194.00  
Completion Date: October-06    
       
T & C  Job  No: 433    
Project Name: Downtown Drainage Improvements
Owner:   City of Corpus Christi  
Engineer:   Urban Engineering  
Project Size:  $5,608,420.00    
Completion Date: May-07    
       
T & C  Job  No: 444    
Project Name: Wastewater Treatment Plant Improvements - 2005
Owner:   Harris County MUD #200  
Engineer:   Jones & Carter    
Project Size:  $   360,000.00    
Completion Date: December-06    
       
T & C  Job  No: 445    
Project Name: Lift Station & W.W.T.P  
Owner:   Fort Bend M.U.D. #57  
Engineer:   Benchmark    
Project Size:  $1,448,540.00    
Completion Date: September-07    
       
T & C  Job  No: 447    
Project Name: Vicksburg WWTP & Lift Station
Owner:   City of Missouri City  
Engineer:   Jones & Carter    
Project Size:  $   941,000.00    
Completion Date: April-07    
       
T & C  Job  No: 450    
Project Name: Avondale Lift Station  
Owner:   Harris County M.U.D.  #393  
Engineer:   Brown & Gay    
Project Size:  $   216,000.00    
Completion Date: Sep-08    
       
T & C  Job  No: 455    
Project Name: Haymarket Lift Station  
Owner:   Harris County F.W.S.D. #51  
Engineer:   Pate Engineers    
Project Size:  $1,031,000.00    
Completion Date: September-07    
       
T & C  Job  No: 456    
Project Name: NW 20 WWTP Expansion  
Owner:   Northwest Harris County MUD #20
Engineer:   R G Miller Engineers  
Project Size:  $1,808,000.00    
Completion Date: Jan-08    
       
T & C  Job  No: 462    
Project Name: Storm Water Pump Station  
Owner:   Baybrook M.U.D. #1  
Engineer:   Terra Associates  
Project Size: $627,000    
Completion Date: Feb-08    
       
T & C  Job  No: 466    
Project Name: WWTP LS & Phase IV WWTP
Owner:   Fort Bend MUD #34  
Engineer:   Carter & Burgess, Inc.  
Project Size: $1,328,000.00    
Completion Date: Mar-08    
       
T & C  Job  No: 473    
Project Name: Linus Area Lift Station  
Owner:   Harris County FWSD No. 1-A  
Engineer:   A & S Engineers, Inc.  
Project Size: $276,000    
Completion Date: Aug-08